A Colorado federal court will allow a contractor to prove up more than $250 million in damages using the modified total cost method (see AECOM Technical Services v. Flatiron AECOM, LLC, Case No. 19-CV-2811, 2024 WL 22640 (D. Co. Jan. 2, 2024)). The AECOM v. Flatiron case involves a Colorado DOT project to add
John Mark Goodman
John Mark Goodman has been with Bradley his entire legal career as a member of Bradley’s Litigation and Construction practice groups. He has an engineering degree from Georgia Tech and a law degree from Virginia. John Mark has had the privilege of representing clients throughout the U.S. and abroad in a wide variety of litigation and arbitration matters, including construction disputes, products liability claims, tax appeals, breach of contract/warranty, patent disputes, trade secret theft, and general commercial litigation.
Court Holds That Contractor Has Duty to Disclose Information Related to the Viability of Pass-Through Claims When Negotiating Pass-Through Settlement Agreement
A Utah federal court recently held that when negotiating a pass-through settlement agreement, a contractor has a duty to disclose information to its subcontractor regarding the viability of the claims to be passed through. See Ludvik v. Vanderlande, 2023 WL 8789379 (D. Utah, Dec. 19, 2023). If it breaches that duty, the contractor may…
Contractor’s Refusal to Sign Broad Lien Waiver Does Not Defeat Mechanics Lien
Recently, the Oregon Court of Appeals reinstated a contractor’s mechanics lien claim notwithstanding the owner’s offer of payment because the offer was conditioned on the contractor signing a broad lien waiver that would have released other claims. See, Development Northwest, Inc. v. Zhiryada, 329 Or. App. 427 (December 6, 2023).
After completing its work, the…
Court Affirms Dismissal of Subcontractor’s Wrongful Termination Counterclaim and Clarifies Scope of Upcoming Trial on Damages
Back in April we examined the court’s decision in Boldt v. Black & Veatch, which dismissed a subcontractor’s counterclaim for wrongful termination on a 60-turbine wind farm project. As you may recall, the subcontractor hired to erect the turbines alleged that it was wrongfully terminated for delays that were not its fault but were…
Court Rejects Differing Site Condition Claim for Lack of Timely Notice
A Minnesota federal court dismissed a tunnelling contractor’s differing site condition claim because notice of the condition was given eight days after the conditions were first observed whereas the contract required notice within three days (see Engineering & Construction Innovations, Inc. v. Bradshaw Construction Corp.). The project at issue involves installation of a…
Court Rejects Contractor’s Claim That COVID-19 Rendered Performance Impossible
A fundamental premise of contract law is that promises must be kept. If legally enforceable promises or “contracts” are not kept, courts may step in to enforce them by ordering performance, awarding damages, or granting some other form of relief. Over time, courts have developed exceptions to the general rule that promises must be kept.
Pay Attention to the Fine Print! Court Enforces Broad Release in Change Order to Deny $25M Claim
A Texas court has rejected a pipeline contractor’s $25 million claim for additional costs based on broad release language include in an executed change order (see Wood Group, USA v. Targa NGL Pipeline Company, LLC, No. 01-21-00542, 2023 WL 5280249 (Tex. Ct. App. Aug. 17, 2023)). The change order at issue increased the contract…
Damages: A Primer for Non-Lawyers in the Construction Industry
You’re in the middle of a job and the party with whom you have a contract breaks a material term of the agreement. What does the law allow you to recover? The answer is found in the law of damages. While the law of damages can vary, some general principles typically apply in most jurisdictions in the…
Liquidated Damages Disproportionate to Actual Damages Deemed Unenforceable
Construction contacts often include provisions that provide for pre-determined or “liquidated” damages in the event of a breach. Such provisions can provide certainty to the parties as to the consequences of a breach and can simplify the task of proving up damages at trial. However, as one contractor found out recently, courts may refuse to…
Grounds for Vacating an Arbitration Award Remain Extremely Limited
The Eleventh Circuit Court of Appeals issued a decision last week upholding an arbitral award, despite the failure of the arbitrators to make certain pertinent disclosures. The case involves an international arbitration before the International Chamber of Commerce (ICC) stemming from the design and construction of the Panama Canal expansion, which was “severely delayed and…