In basketball there is a shot clock. Once a team has the ball, it must shoot within 30 seconds. We’re obviously talking about college basketball since its March, but the NBA has a similar 24-second shot clock. Failure to shoot within the required time automatically gives the ball back to the other team. The law’s…

The Eighth Circuit Court of Appeals has affirmed a jury verdict finding that a developer and its founder defrauded a contractor by misrepresenting the availability of construction funding. See Selective Ins. Co. of Am. v. Heritage Const. Cos. et al, Case No. 24-2333, 2026 WL 263591 (D. Minn. Feb. 2, 2026). The case involves construction of a…

Recent reports and contractor experiences suggest that the U.S. Agency for International Development (USAID) has, in some instances, failed to timely pay contractors for work that has already been performed and accepted. While payment delays are not unprecedented in federal contracting, prolonged or systemic nonpayment raises serious legal and practical concerns — particularly for contractors…

A federal judge in Oregon has tossed a subcontractor’s unjust enrichment or “quantum meruit” claim against the owner because the subcontractor did not first exhaust its contractual remedies against the contractor. 

Exhaustion of remedies is a common legal doctrine that generally requires parties to pursue relief in a particular order. In dealing with appeals from a…

Many construction contracts include a provision that prohibits the parties from recovering “consequential” damages in the event of a breach. Sometimes parties will negotiate and agree to a waiver of consequential damages that identifies and describes what damages are considered consequential damages. For example, the parties may agree that prohibited consequential damages include such damages as…

A federal judge in Oklahoma last week ruled against an electrical subcontractor who quit work before finishing because it was allegedly unsafe to continue. The court found that the subcontractor was simply losing money, and that the safety excuse was a “post-hoc fabrication” to justify “jumping ship.”

The case involves construction of a renewable natural gas…

Court Affirms $1 Nominal Damage Award in Wind Farm Construction Dispute

The general contractor on the 60-turbine wind farm project in Good Hope, Illinois, is entitled to collect a whopping $1 on its cost-to-complete claim against its terminated subcontractor. We previously reported on the court’s entry of summary judgment in favor of the general contractor…

A California appeals court has upheld a $5 million award in favor of Whiting-Turner Contracting Company and against the owner of a 12-story, Virgin-brand hotel in San Francisco. Whiting-Turner agreed to construct the hotel for a guaranteed maximum price of $36 million pursuant to a modified AIA standard form agreement and general conditions. The contract called…

A federal court in upstate New York is permitting a subcontractor’s delay claim to proceed notwithstanding a “no damages for delay” provision in the subcontract. The case, The Pike Company, Inc. v. Tri-Krete, Ltd., involves delay claims asserted by a subcontractor hired to install pre-cast concrete walls on a college dormitory project. The subcontractor alleges that…