In today’s market, contractors often find themselves playing The Price is Right when bidding material costs — trying to hit the number just right without going over. But with new (and changing) tariffs targeting steel, aluminum, and other goods in 2025, that guessing game just became even riskier.

Should contractors base bids on current prices

A California appeals court has upheld a $5 million award in favor of Whiting-Turner Contracting Company and against the owner of a 12-story, Virgin-brand hotel in San Francisco. Whiting-Turner agreed to construct the hotel for a guaranteed maximum price of $36 million pursuant to a modified AIA standard form agreement and general conditions. The contract called

Government contracts often include a termination for convenience clause, generally allowing federal agencies to cancel agreements when it serves the government’s interest. While this power is fairly broad, it is not absolute — and when misused, contractors may have legal recourse. Several court cases highlight situations where termination for convenience was found to be an

Hark! A recent Alabama Supreme Court indemnity decision, Mobile Infirmary Association v. Quest Diagnostics Clinical Laboratories, may require you to retrieve your drafting pen. Although not a case involving a construction dispute, Mobile Infirmary does address a key component of risk shifting in construction contracts — the indemnity clause. Put simply, contractual indemnity is

A Texas court has rejected a pipeline contractor’s $25 million claim for additional costs based on broad release language include in an executed change order (see Wood Group, USA v. Targa NGL Pipeline Company, LLC, No. 01-21-00542, 2023 WL 5280249 (Tex. Ct. App. Aug. 17, 2023)). The change order at issue increased the contract

The Texas Supreme Court recently provided new guidance in interpreting force majeure language in an oil and gas drilling dispute. In Point Energy Partners Permian, LLC v. MRC Permian Company, the court held that the oil and gas lessee’s scheduling error linked to a well collapse 60 miles from the lease site at issue

Here’s the Scenario:

After months of working with a new developer client (and providing hours of unreimbursed value engineering) and hard negotiations over the cost plus GMP contract (fighting over indemnity/escalation/savings/liquidated damage clauses), you have a deal. You pop a cork with all involved since the developer has said this is one of many

You’ve Gotta Fight For Your Right To Get Paid: The Right To Stop WorkA contractor is halfway through the (timely) completion of a project and the owner’s payment is late. Days, weeks go by, and now the contractor is incurring all the costs of the work without any compensation. It might be tempting to simply walk off the job, but bear in mind that legally speaking, that might