All breaches are not created equal. A minor, technical breach may be deemed “immaterial.” Other breaches – so-called “material” breaches — deprive the non-breaching party of something important or essential to the purpose of the contract. Whether a breach is material or immaterial is normally a question for the finder of fact. The answer determines what remedy

A recent decision from the U.S. District Court for the Southern District of Florida demonstrates how facts supported by documents generated during the project can be vital to prime contractor/subcontractor disputes. In Berkley Ins. Co. v. Suffolk Constr. Co., No. 19-23059-CV, 2024 WL 3631226 (S.D. Fla. July 22, 2024), following a two-week bench trial

The Federal Court of Claims recently ruled in favor of the operator of the Vermont Yankee nuclear power plant in its long-running dispute with the United States over the disposal of spent nuclear fuel (NorthStar Vermont Yankee, LLC v. United States, No. 18-1209C, 2024 WL 3563239 (Fed. Cl. July 29, 2024)). Pursuant to a statutory

I have practiced law for 40 years with the vast majority as a “construction” lawyer. I have seen great… and bad… construction lawyering, both when representing a party and when serving over 300 times as a mediator or arbitrator in construction disputes. To be clear, I have made my share of mistakes. I learned from

Construction law is largely a matter of contract law. Yes, there are federal and state statutes that deal with construction issues and, yes, construction cases sometimes involve tort claims, but more often than not, construction disputes revolve around the parties’ contract. What constitutes the parties’ contract is frequently undisputed. As one developer learned last week, that is

The Second Circuit Court of Appeals recently applied a no-damages-for-delay provision to affirm the dismissal of a demolition contractor’s breach of contract claims. The project involved reconstructing and raising the Bayonne Bridge between Staten Island and New Jersey.  The Port Authority awarded the general contract on the $1.29 billion project to the joint venture Skanska

Construction contracts often include clauses that purport to limit the liability of one or both parties. This includes clauses that completely prohibit any claims for certain types of damages such as lost profits and other consequential damages, extended overhead or other “delay” damages, and exemplary/punitive damages. Contracting parties may also include clauses that purport to cap liability

The court in AECOM v. Flatiron is back at it issuing additional evidentiary rulings as the parties head to trial later this month. These latest rulings highlight the risk of seeking the same damages from multiple parties, sometimes referred to as “fighting on two fronts.” As you may recall, AECOM v. Flatiron involves claims by